Makeoff data report · November 2026

The Transformer Gap: A Takeoff Checklist for Quote-First Bids

What 144 Makeoff findings show about the scope between the transformer quote and the takeoff, and an 8-point transformer takeoff checklist to catch it.

144Transformer scope findings
61 of 64Findings beyond the transformers that were installation and connection scope
20 hrsMedian labor per transformer line on customer takeoffs

Source: Makeoff production database · 60 projects, 22 electrical contractors · Apr 1 – Nov 18, 2026

Executive summary

Low-voltage dry-type transformers usually ride the gear quote, often beside the panelboards they feed. Makeoff's data shows it on two jobs: all ten transformers flagged missing on an early upload appear by tag on the contractor's later distribution quote. The misses that hold up are the feeders, grounding and supports around each transformer. The transformer takeoff checklist at the end of this paper lists what to check when you build labor off the quote.

Between April 1 and November 18, 2026, Makeoff raised 144 unique missing-item findings tied to Section 26 22 00, Low-Voltage Transformers. They span 60 projects from 22 electrical contractors and exclude existing and owner-furnished equipment. Eighty flagged a missing transformer; this paper treats those as the quote-first workflow, not misses. That leaves 64.

  1. Nearly everything left is installation scope

    Sixty-one of the 64 were primary and secondary feeders, separately derived grounding, pads, hangers and isolators, and primary breakers. Most of that work has to be counted in the takeoff.

  2. Feeders lead

    Thirty-seven findings named a transformer's primary or secondary feeder, 14 of them on working takeoffs. On one, the takeoff carried eight transformers but none of their primary feeders.

  3. Contractors set aside the transformer, not the installation

    They ignored 10 of the 80 transformer findings, the most of any gear in this series. They recorded a decision on 8 of the 61 installation findings and ignored none of them.

  4. Makeoff's transformer read is benchmarked

    Against estimators' own takeoffs on 21 projects, Makeoff's gear list carried 76 of the 82 transformers they priced (93%) as run, and every disagreement traced back to the drawings.

Key figures

MeasureFigure
Data windowFindings created April 1 to November 18, 2026; customer findings fall between April 28 and August 28
Transformer findings (Section 26 22 00)144 unique missing-item findings on 60 projects from 22 electrical contractors
Findings that flagged the transformer itself80 of 144, treated as quoted rather than missed
Installation and connection findings61 of the other 64
Feeder findings37, each naming a transformer's primary or secondary feeder
Median labor per transformer line20 hours per unit (middle half 14 to 26), from 200 lines on 130 customer takeoffs
Makeoff's transformer recall, as run92.7% (76 of 82 priced transformers) on 21 benchmark projects

How transformer scope gets priced

A dry-type transformer reaches the bid through the gear quote or a single takeoff line. The work around it reaches the bid only if someone counts it.

In a quote-first bid, the estimator leaves the transformer for the gear quote and builds its labor off that quote rather than taking it off on the first pass.

First-pass takeoff. The estimator takes off feeders, panels and branch work. A transformer may get a line for labor, or be left for the quote.

Gear quote. Dry-type transformers usually come with the panelboards on the distribution quote, sometimes with lug kits and vibration pads.

Labor built off the quote. Labor to set, hang or mount each unit and terminate it, priced from the quote's equipment list.

The gap opens between the first pass and the labor build-up. If the transformer is left for the quote, nothing in the first pass prompts a count of its feeders, grounding and supports, and labor built off the quote prices only what the quote lists. Here is where each piece of transformer scope usually lands:

ScopeUsually carried onRisk in a quote-first bid
Dry-type transformerGear quote, often with the panelboardsLow, once the quote is leveled against the one-line
Lug kits, vibration pads, wall bracketsGear quote, if the spec lists themOptions vary by quote
Primary breaker in the source boardGear quote or takeoffScheduled on the board, missed in the count
Primary feeder from the source breakerTakeoffEasy to skip between the source board and the unit
Secondary feeder to the panelTakeoffShort, heavy runs that get treated as part of the panel
Separately derived system groundingTakeoffEach unit needs a system bonding jumper and grounding electrode conductor (NEC 250.30)
Housekeeping pad, hangers, isolators, seismic bracingTakeoffBuried in general notes and seismic details

How the assumption changes the count

Set aside as expected · 80

Transformers

Assumed quoted, with labor built off the quote

80

Counted as findings · 64

Installation and connection

Feeders, grounding, pads, hangers, isolators and primary breakers

61

Other

Findings with no mapped spec section

3

The numbers: 144 transformer findings across 60 projects

Of the 144 transformer findings, 80 flagged the transformer itself. Setting those aside leaves 64, and 61 of those are installation and connection scope.

Beyond quoted transformers, nearly every finding is installation scope

61 of 64 findings outside the transformers are installation and connection scope

Working takeoff: raised against a takeoff that already had line items (57 findings)Drawings only: raised on drawings uploaded before any takeoff was loaded (87 findings)
TotalWorking takeoffDrawings only

Transformers: set aside as expected · 80 findings

Transformers802852

Installation and connection: carry in the takeoff · 61 findings

Primary & secondary feeders371423
Grounding & bonding1266
Pads, hangers & isolation853
Primary breakers431

Other · 3 findings

Spec section unmapped312
Makeoff production database · 144 unique missing-item findings, Apr 1 – Nov 18, 2026, excluding existing and owner-furnished equipment.

On working takeoffs, 29 findings remain after the transformers: 28 installation items and one unmapped spec section. Across both kinds of finding, the 56 installation findings with an estimate carry about $620K of estimated value, $535K of it feeders.

Transformer findings are uncommon: about 1% of the 11,195 missing-item findings Makeoff raised for customers in the window. For what estimators miss across all scope, see our Where Mistakes Hide report.

How well Makeoff reads transformers

Every finding in this paper starts with Makeoff's gear list: before it can flag a missing transformer or the feeder to it, Makeoff has to find the unit on the drawings.

Makeoff's takeoff agreement benchmark tests that read against estimators' own takeoffs. Transformers are the second most common gear item in it after panelboards, with 82 units priced on 21 of the 53 projects scored in September and October 2026. The test method and first-batch results across all gear are in the Takeoff Agreement Benchmark report.

MeasureAs runAfter review against the drawings
Recall: transformers the estimator priced that Makeoff listed92.7% (76 of 82)100% (82 of 82)
Precision: transformers Makeoff listed that the estimator priced93.8% (76 of 81)97.6% (82 of 84)

Every disagreement traced to the drawings. Six priced units were missing as run. Three were marked existing on the drawings and were excluded as not new gear. The other three were in Makeoff's export text but dropped by a Makeoff comparison rule, and were credited on review. Five units Makeoff listed were not priced. Three of them sat on a public high school's transformer schedules: XCL at 75 kVA, X3F at 112.5 kVA and XPG at 45 kVA. The takeoff priced the panels they feed but not the transformers, the same pattern behind the 80 transformer findings in this paper. The other two stand as disagreements.

Sizes come through less often. In the second batch, 36 of the 59 transformers Makeoff found carried a kVA in the drawing text, and all 36 matched the estimator. The other 23 had none to read: those drawings had no transformer schedule, and the kVA sat on the one-line as a number beside the symbol, which the export drops. Sixteen of the 23 were on one hotel. Counting type and rating together, second-batch recall is 58% (36 of 62). Makeoff lists such units as unrated, beside the primary breaker, feeder and panel the drawings do give, so the estimator sets the size before the quote goes out. That matters for the first checklist item below, which matches the quote by tag and kVA.

The benchmark at a glance

76 of 82Priced transformers Makeoff listed, as run
36 of 36Sizes read that matched the estimator
21Projects with priced transformers

Transformers: expected, not missed

Eighty findings flagged a transformer with no takeoff line, 52 of them from drawing reviews before any takeoff was loaded. In a quote-first bid, that is what the first pass should look like.

The quotes list them. On two jobs, every transformer flagged missing shows up by tag on the contractor's later distribution quote:

Project typeTransformers flagged missingOn the later quoteContractor's response
Student housing, 50% SD setSeven, from 15 to 112.5 kVA, including GX1DPLA, GX1LP and CUPXDPLAAll seven, on a $3.37M quote for the 100% SD setOpen
Industrial plantTX-T2 (75 kVA), TX-T5 (45 kVA), TX-T6 (30 kVA)All three, same tags and ratings, on an $87,805 quoteIgnored all three

Contractors ignored 10 of the 80 transformer findings, more than for any other gear in this series. That fits a workflow where the transformer is already priced somewhere else.

Transformer labor hours: what contractors carry

Unlike generators and switchboards, transformers often appear as takeoff lines: 200 of them on 130 customer takeoffs from 38 contractors. Labor on those lines ran a median of 20 hours per unit (14 to 26 hours for the middle half), about 21% of the line's value. Only 5 of the 200 carried no labor. Setting the unit is rarely the gap; connecting it is. The work around the transformer is where the checklist below applies.

20 hrsMedian labor per transformer
14–26Middle half, in hours
5 of 200Lines with no labor on the line

Transformer installation and connection: what the labor build-up misses

Sixty-one findings named the work around a transformer: 37 feeders, 12 grounding packages, 8 pad, hanger and isolation items, and 4 primary breakers.

They total about $620K across the 56 with an estimate.

Examples from working takeoffs

Corporate headquarters · 616 lines

Transformers carried, primary feeders not

The takeoff had two 45 kVA and six 75 kVA transformers. The transformer schedule sizes each primary feeder, 3#4 or 3#1 copper in 1-1/4 or 1-1/2-inch conduit. None were carried. Reviewed.

Manufacturing plant · 536 lines

A scheduled primary feeder

Feeder 125-3G, three #1 copper and a #6 ground in 1-1/4-inch conduit, from HMB to T-LMB. The contractor's note: "Good catch."

Multifamily · 472 lines

Suspended transformers

Notes require 75 kVA and smaller units hung from the slab on rods with spring isolators, with seismic bracing. None of it was carried.

Industrial plant · 287 lines

Isolation pads

A general note requires 0.5-inch-deflection neoprene pads under five transformers. Est. $2.5K.

Hospital · 263 lines

Separately derived grounding

The one-line shows secondary grounding conductors sized through to the service, plus a ground-rod detail. The takeoff had only small grounding items. Est. $3.5K.

School, 3,974 lines · industrial plant, 829 lines

Secondary feeders

Panel LP-4g, fed from T-4b, and Panel D, fed from T-D, had no traceable feeder.

Not every finding held up. On a federal research facility, the contractor marked a primary-feeder finding "it is in the xfmr assembly." On another job, the takeoff carried aluminum secondaries where the one-line called for copper, and Makeoff flagged them as missing rather than as a substitution.

What contractors did with the findings

Contractors recorded a decision on 28 of the 144 findings.

OutcomeFindingsWhat they were
Completed6Four transformers from 75 to 150 kVA, and two breakers feeding transformers
Reviewed11Five transformers and six feeders, including "it is in the xfmr assembly"
Ignored10All transformers, including three later found on the contractor's quote
Resolved1A 150 kVA transformer
Open116No decision recorded in Makeoff, which does not mean the finding was wrong

Every ignored finding was a transformer. The eight installation findings with a decision, six feeders and two breakers, were all completed or reviewed. For how one estimating group acted on Makeoff findings over eight weeks of live bids, read five scope misses caught on live competitive bids.

Transformer takeoff checklist: 8 checks for building labor off the quote

When the gear quote comes in and you build its labor, check each item against the quote and the takeoff. Most items came up as findings in this data set.

Confirm which quote carries it

3 checks

Add to the takeoff

5 checks

Want a second set of eyes on your next transformer job?

Send us a bid you already priced, and Makeoff will flag the scope the takeoff doesn't carry.

Review my next bid

Transformer scope FAQ

What should a transformer takeoff include?

Every transformer on the one-line and schedule, matched by tag and kVA to a gear quote or a takeoff line, plus the work that connects it: the primary breaker in the source board, the primary feeder from that breaker, the secondary feeder to the panel, separately derived system grounding, and the pads, hangers, isolators and seismic bracing the notes call for. Labor to set, hang or mount and terminate each unit goes in too.

What is a quote-first bid?

A quote-first bid is an electrical bid where the estimator leaves major gear, such as transformers, for the vendor's gear quote and builds the installation labor off that quote instead of taking the gear off on the first pass. The risk is the work around the gear, such as feeders, grounding and supports: labor built off the quote prices only what the quote lists.

Are dry-type transformers included in the gear quote?

Usually. Dry-type transformers often come with the panelboards on the distribution quote, sometimes with lug kits and vibration pads. On two jobs in Makeoff's data, every transformer flagged missing on an early upload appeared by tag on the contractor's later quote. The feeders, grounding and supports around each unit are usually left to the takeoff.

How many labor hours does it take to install a dry-type transformer?

On 200 transformer lines priced at $2,000 or more per unit on 130 Makeoff customer takeoffs from 38 contractors, labor ran a median of 20 hours per unit, with the middle half between 14 and 26 hours. That is labor on the transformer line only. Feeders, grounding and supports are separate.

What transformer scope do electrical takeoffs miss most?

Feeders. In Makeoff's data, once quoted transformers are set aside, 61 of the remaining 64 findings were installation scope, and 37 of those named a transformer's primary or secondary feeder. The rest were 12 grounding packages, 8 pad, hanger and isolation items, and 4 primary breakers.

What is Section 26 22 00?

Section 26 22 00, Low-Voltage Transformers, is the MasterFormat section in Division 26, Electrical, for dry-type transformers rated 600 volts and below, such as the 480-to-208Y/120-volt units that feed building panelboards. Medium-voltage and utility transformers are specified elsewhere and are not covered in this paper.

How accurately does Makeoff read transformers on electrical drawings?

In Makeoff's takeoff agreement benchmark, scored against estimators' own takeoffs on 21 projects in September and October 2026, Makeoff's gear list carried 76 of the 82 transformers the estimators priced (92.7%) as run. Of the six it missed, three were marked existing on the drawings and three were dropped by a Makeoff comparison rule. Sizes come through less often: in the second batch, 36 of the 59 transformers Makeoff found carried a kVA in the drawing text, and all 36 matched the estimator.

About the data

Scope and method

This paper covers missing-item findings tied to Section 26 22 00, Low-Voltage Transformers, and the work that connects a transformer to the building.

Window
Findings created April 1 to November 18, 2026. Customer findings in this category fall between April 28 and August 28.
A finding
A published "missing item" finding, meaning the drawings or specs require scope the takeoff does not carry. Retired, suppressed and merged findings are excluded.
Transformer scope
Findings whose title names a low-voltage transformer by tag, rating or type, its feeders, grounding, supports or primary breaker, or Section 26 22 00.
Left out as other scope
Utility and medium-voltage transformers with their pads, bollards and service conduits; lighting drivers and fixture types tagged "T"; panels named T-something; control transformers furnished by mechanical; and sheet references.
Quote-first assumption
A missing transformer is treated as expected, because it is quoted and its labor built off the quote. These 80 findings are reported but not counted as misses.
Existing and owner-furnished equipment
Excluded. This removed a feeder to an existing transformer and a bond tied to existing gear.
Superseded drawings
Ten findings on sets the customer labeled outdated are excluded.
Two kinds of finding
57 were raised against a takeoff that already had line items. 87 came from drawings uploaded before any takeoff existed.
Dollars
Makeoff's pre-buyout estimate of installed cost, not the contractor's price.
Accounts
Makeoff internal and demo accounts are excluded. Seven repeats on re-uploaded copies of the same project are counted once.

Limitations

  • Quote-first is an assumption about typical workflow. The quote match covers two jobs, where tags line up between an early upload and a later quote upload of the same job.
  • Low-voltage versus medium-voltage is a boundary call. Units with a medium-voltage primary, such as 13.8 kV, and utility transformers were excluded.
  • Existing and owner-furnished screening relies on the drawings. Most findings do not say whether a unit is new or existing. Units not marked existing or owner-furnished were kept.
  • Takeoff state is reconstructed. Whether a takeoff existed when a finding was raised is inferred from line-item creation times.
  • Matching uses finding titles. Transformer scope described without naming the unit is not counted.
  • Dollar estimates are Makeoff's, made before buyout.
  • Labor benchmarks come from 200 transformer lines priced at $2,000 or more per unit on customer takeoffs to date. They cover labor on the transformer line only.
  • Accuracy figures come from a separate benchmark, Takeoff Agreement Benchmark: Low-Voltage Transformers. It compares Makeoff's gear list with estimators' takeoffs on 21 projects and does not score this paper's findings directly. Its second-batch review decisions are drafted, not yet filed, and the after-review figures follow the drafts. First-batch rating agreement is not broken out for transformers.
  • Missing-item findings only. Line-item errors, contradictions and code findings are not included.
  • Companion papers: The Switchboard Gap, The Transfer Switch Gap and The Generator Gap. Service conduits from customer-owned transformers to the main switchboards are counted in the switchboard paper, not here.
  • Customer names are withheld. Projects are described by building type.

Source: Makeoff production database, queried November 18, 2026. Accuracy figures: Makeoff Takeoff Agreement Benchmark: Low-Voltage Transformers, November 2, 2026.

To cite this report: Makeoff, “The Transformer Gap: A Takeoff Checklist for Quote-First Bids,” November 2026, https://www.makeoff.com/reports/transformer-takeoff-checklist.

About Makeoff

Makeoff reviews electrical bids against the drawings and specs and flags scope the takeoff doesn't carry, like the transformer feeders and grounding in this paper. To see what it flags on one of your bids, visit makeoff.com.

About the author

Will Zacher is the CEO of Makeoff.