Makeoff · Case study

Electrical Bid Review: Five Scope Misses Caught on Live Competitive Bids

Eight weeks of bid review inside the electrical group of an Upper Midwest specialty contractor.

“It’s a checkpoint. It’s another me going through, looking at our estimates and projects and pointing out the things that can be very costly if missed.”
Chief Estimator
Customer
Multi-trade specialty contractor
Region
Upper Midwest
Division
Electrical estimating
8 weeks
Live pilot on real competitive bids
5
Verified catches, confirmed by estimators
5
Custom checks written by their team

An electrical estimating group ran Makeoff bid review on live competitive bids for eight weeks and confirmed five catches their own review had not surfaced. The estimator who owned each project verified every one before pricing closed. Two of the five were sitting in addenda that contradicted a drawing note the team had already priced against.

The team worked inside their existing process. Estimators exported the takeoff from Accubid, uploaded the plans and specs, and let Makeoff read the set together before the bid went out. The chief estimator called it dump and go.

Five scope conflicts caught on live bids

Verified on live bids during the pilot, each confirmed by the estimator who owned the project.

Makeoff bid review flagging a spec and drawing conflict on an electrical plan set
Image slot 1 · replace with a bid review screenshot
01
Addendum against a drawing note
Door hardware scope conflict
The addendum assigned all hardware to the electrical contractor while a drawing note gave door hardware to others. The chief estimator settled it with his supplier before pricing closed.
02
A mid-cycle addendum
Pole heights: 22 ft carried, spec required 30 ft
Thirty-foot poles cost more to manufacture and set, and that difference would have shown up after award.
03
Means and methods, buried in the spec text
Concrete encased duct bank
Encasement changes how the run gets built and what it costs to install. The chief estimator on this one: “That’s the exact type of thing we want.”
04
Subcontractor pricing, off the extension
Protective bollards at the utility transformer
An item that sits between trades, where each side assumes the other picked it up.
05
Spec-to-drawing cross-check
AV stub-ups: 1 in. carried, spec required 1.25 in.
The spec called for the larger conduit in four locations. No drawing note said so.
“Just the site lighting plans, we had a whole bunch of light poles. It was flagged, it was wrong, so we were able to go in there and adjust that.”
Chief Estimator, describing the pole catch to a third party months later

Across the pilot the money added up.

“We found some pretty substantial dollar amounts of items that we did not have covered with our initial estimates.”
Chief Estimator

Why spec and drawing conflicts get missed

“It helps you sleep at night. It’s all the things you worry about in the background, that keep you up at night.”
Chief Estimator

Every one of these was obvious to the estimator the moment they saw it next to its source. The difficulty is structural. Read on its own, each document in a bid package looks finished, and a conflict only shows up when you hold two of them against each other. That comparison takes time, which is the first resource to go in a week with four bids due, and the documents keep changing while it happens.

Addenda make it harder. They arrive late, sometimes the same week as bid day, and estimators read them for the thing they are expecting rather than checking them against everything already priced. Two of the five catches came in that way, including the pole heights.

Everything on this list was stated plainly somewhere in the package. What turned each item into risk was a second document saying something different, in a place nobody had reason to look.

Before the pilot, they tried building it themselves

This team came to Makeoff after an internal attempt.

“We were deeply interested in AI, how can AI assist us with what we do. We had started to dabble in it. One of our guys is fairly in tune with working with AI, so he was trying to build something. We were stumbling through processes.”
Chief Estimator

The gap between a general purpose model and a bid review that reads a plan set the way an estimator does is most of the work. That gap is what took eight weeks of live bids to close, and it is why the checks below could be written by estimators rather than engineers.

The estimators wrote their own bid review checks

Midway through the pilot the chief estimator and a senior estimator started writing checks of their own. Five of them, built in the customizable Issue Flagger, encode how this firm bids its work. Makeoff runs those five on every project the team uploads now, including the ones that arrive in week three of a crunch.

Custom Issue Flagger checks written by an electrical estimating team
Bid bond and go/no-go
Pulls the bond requirement and tax status before anyone commits time to the pursuit, along with the prevailing wage determination.
Low voltage under EC scope
Which low voltage systems land in the electrical contractor’s scope.
OFCI requirements
Owner furnished, contractor installed items, called out where they appear.
Design build requirements
Where design responsibility shifts onto the contractor.
Specified manufacturers
Named and basis-of-design manufacturers for gear and equipment.
And more since
The library grows with the team’s standards.

What we shipped during the eight-week pilot

The estimators asked for things while they worked and we built them. Four shipped inside one quarter.

A closeout tab import that cleared false positives on quoted and subcontracted scope
The customizable Issue Flagger
A vendor quote check, now in beta
A direct Accubid API integration, in development
“They’ve taken ideas that we’ve had and very rapidly brought them into fruition.”
Chief Estimator

What it took to run it

Nothing about the pilot required the team to change how they estimate.

“A very simple uploading of the drawings, the specs, you can export your takeoff. Through a couple minute upload time, seeing the quick and easy results.”
Chief Estimator
“The system itself is very, very user-friendly. Impressive with how fast it works.”
Chief Estimator

How bid review fits into bid day

Makeoff is a review layer for electrical estimating. It reads the drawings and the specs together, the way a senior estimator would with unlimited time, while there is still room to price what it finds. The estimator owns every number, and Makeoff catches what falls between the documents on the way to bid day.

Questions about electrical bid review

What is bid review in electrical estimating?

It is the pass where the drawings, the specs, the addenda, and the takeoff get held against each other before pricing closes. Takeoff counts what is drawn. Review asks whether the documents agree about what is being bought.

Why do spec and drawing conflicts get missed?

Because each document reads as complete on its own. A conflict only exists across two of them, and finding it means reading both at once against a takeoff that is still moving.

How late can addenda change electrical scope?

Bid week is normal. Two catches in this pilot arrived that way, and the pole height change would have cost the contractor after award.

Can an estimating team build this internally?

This one tried. They had someone comfortable with AI working on it and described the process as stumbling. Reading a plan set the way an estimator reads it is where the effort sits.

Does Makeoff price the job?

No. Every number belongs to the estimator. Makeoff flags what the documents disagree about and hands it back with the source.

Why this customer is not named
Bid review findings are a record of what almost went out the door, and no estimating group wants its misses attached to its name where owners and competitors can read them. The catches above are reported as they occurred, and the quotes come from a reference call the chief estimator gave to third parties. The company stays unnamed unless they say otherwise.